A de-snagging inspection in Dubai is a second visit after the developer has repaired the defects from the first snagging report. The inspector re-checks every original point and marks it Resolved or Not Resolved, with a new photo beside the original. On a recent Palm Jumeirah apartment, most electrical and plumbing repairs were complete. Some finishing work was still open, even though the developer had said everything was done.
By the qualified civil engineers at The Snag Master, a RERA-certified, InterNACHI-accredited inspection company serving all seven UAE emirates.
Case Study at a Glance
| Property | High-end apartment, two bedrooms and a study |
| Community | Palm Jumeirah, Dubai |
| Service | De-snagging re-inspection (second visit) |
| Areas covered | 11, from the entrance to the balcony |
| Report | 56 pages, each point marked Resolved or Not Resolved with before and after photos |
The Situation: “The Repairs Are Done”
Our client was buying an apartment on Palm Jumeirah. We had already completed the first snagging inspection and handed over a report of everything that needed attention. The developer then carried out repairs and told the client the work was complete.
Before accepting the keys, the client asked us to go back and check. That is the right instinct. A verbal “it’s all fixed” is a promise, and a re-inspection turns that promise into evidence.
What Is a De-Snagging Re-Inspection?
A de-snagging re-inspection is not a fresh inspection. It is a check against an existing list. For a full definition, see our guide to snagging vs de-snagging in Dubai.
On this job, we took the original report and walked the apartment again, area by area. We opened the same doors and tested the same switches, taps and fittings. We photographed each spot again from the same angle, so every point shows the original photo and the new photo side by side.
The 11 areas covered:
- Entrance and powder room
- Living area and kitchen
- Laundry room and study
- Bedroom and bedroom bathroom
- Master bedroom and master bathroom
- Balcony
What We Found on the Second Visit
What the developer fixed well
The building-services repairs had largely been completed to a good standard:
- Loose or misaligned sockets and switches were fixed to the wall and straightened.
- Exposed wires at conduit ends were tidied away.
- Loose bathroom fittings, including taps, the spray hose holder and towel hangers, were secured.
- A bathtub sitting out of line, with an unfinished gap at its base, was corrected.
- A concealed sprinkler and a fire alarm speaker that had not been finished off properly were fixed.
What was still open
The remaining items were mostly finishing work, the kind that is easy to sign off from across a room:
- Uneven paint and plaster on some ceilings, plus a ceiling crack
- Wallpaper with a visible joint, stains and frayed edges
- Doors that did not match their frame colour, and loose door handles
- Missing screw caps inside cabinets and wardrobes
- Strip lights that stayed on after the switch was turned off
- A damaged floor tile and scratches on the balcony glass
These are what we saw on the day. They are not a judgement on any developer. They show why every point needs checking.
Why Finishing Items Get Missed
A completion list tells you what was worked on. It does not tell you whether the work was finished properly. Repairs to wiring and plumbing tend to be tested and signed off. Cosmetic items are often only glanced at.
Some of these open items matter more than they look:
- A strip light that stays on after switching off can point to a wiring or switch fault.
- A ceiling crack can hide a moisture or movement issue.
- Loose handles and missing caps become your maintenance costs once you accept the property.
The Outcome
The client received a 56-page re-inspection report with a clear answer for every point: done or not done, with photos to prove it. Instead of relying on a verbal assurance, they had a precise list of open items to send back to the developer before accepting the apartment.
When to Book a De-Snagging Inspection in Dubai
Book it after the developer says repairs are complete and before you sign to accept the property. Once you accept, proving that a defect existed at handover becomes harder. Inspections within the Defect Liability Period are also worth planning for. Read more in our property snagging service overview.
Re-inspections suit:
- Off-plan buyers taking handover of apartments, villas and townhouses
- Investors who need a documented condition record
- Owners who raised a long snag list and want it independently verified
Why Choose The Snag Master
- Qualified civil engineers, not general technicians
- RERA-certified and InterNACHI-accredited, following the RICS code of practice
- Same-angle before and after photos for every point
- Clear Resolved / Not Resolved labels you can send straight to your developer
- Coverage across all seven emirates: Dubai, Abu Dhabi, Sharjah, Ajman, Ras Al Khaimah, Umm Al Quwain and Fujairah
Learn more about our RERA-certified inspection approach, or our residential inspection service for villas and apartments.
Frequently Asked Questions
What is a de-snagging inspection?
It is a second visit after the developer has repaired the snags from the first inspection. We check every point from the original report and mark each one Resolved or Not Resolved, with a new photo beside the original.
Why not just trust the developer’s list of completed repairs?
A completed list shows what was worked on, not whether it was finished properly. In this Palm Jumeirah apartment, most electrical and plumbing repairs were done, but some finishing work was still open.
When should I book a de-snagging re-inspection?
After the developer says repairs are complete and before you sign to accept the property.
What does the re-inspection report look like?
It has one entry per point from the first report, each with the original photo, the re-inspection photo and a Resolved or Not Resolved label. For this apartment it ran to 56 pages.
Is a re-inspection the same as a new inspection?
No. A re-inspection checks the existing list. If something new is spotted on the day, it can be noted, but the main job is confirming the original points.
Your Developer Says the Snags Are Fixed? Have Them Checked Before You Accept.
The Snag Master’s RERA-certified civil engineers will re-check every point from your original report and send you a photo-backed Resolved / Not Resolved report within 24 hours, so you know exactly what’s still open before you accept the keys.